Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the updraftplus domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /code/wp-includes/functions.php on line 6121

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wpforms-lite domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /code/wp-includes/functions.php on line 6121

Notice: A função _load_textdomain_just_in_time foi chamada incorretamente. O carregamento da tradução para o domínio noticiasdoacre foi ativado muito cedo. Isso geralmente é um indicador de que algum código no plugin ou tema está sendo executado muito cedo. As traduções devem ser carregadas na ação init ou mais tarde. Leia como Depurar o WordPress para mais informações. (Esta mensagem foi adicionada na versão 6.7.0.) in /code/wp-includes/functions.php on line 6121
Deracre inicia obras de recuperação no aeródromo de Marechal Thaumaturgo – Noticias do Acre
Notice: Undefined index: noticiasdoacre-content in /code/wp-content/themes/agenciaac-wp/inc/template-functions.php on line 79

Notice: Trying to get property 'src' of non-object in /code/wp-content/themes/agenciaac-wp/inc/template-functions.php on line 79

Notice: Undefined index: noticiasdoacre-content in /code/wp-content/themes/agenciaac-wp/inc/template-functions.php on line 79

Notice: Trying to get property 'ver' of non-object in /code/wp-content/themes/agenciaac-wp/inc/template-functions.php on line 79

Deracre inicia obras de recuperação no aeródromo de Marechal Thaumaturgo

Recuperação do pavimento e demais ações de manutenção e limpeza estão sendo realizadas (Foto:Cedida)

O governo do Estado, por meio do Departamento de Estradas de Rodagem do Acre (Deracre), iniciou na última semana os serviços de recuperação da pista do aeródromo de Marechal Thaumaturgo.

Cerca de 360 sacas de cimento, 40 metros cúbicos de areia e de brita e seis toneladas de camada asfáltica e diversos maquinários foram encaminhados para o município por meio de balsas que saíram do porto de Cruzeiro do Sul.

“Com a reforma na pista do aeródromo, vamos melhorar o fluxo de transporte de serviços essenciais que só chegam a Marechal Thaumaturgo por aviões, além de gerar mais segurança durante os pousos e decolagens”, destaca o diretor-presidente do Deracre, Cristovam Moura.

Os serviços de recuperação do pavimento e demais ações de manutenção e limpeza estão sendo feitos pelas equipes técnicas da instituição.

“Iniciamos as primeiras frentes de serviço na pista do aeródromo, e nos próximos dias outra balsa com equipamentos e insumos deve ser enviada para complementar as ações”, relata o gerente do Deracre no Juruá, Josinaldo Batista.